Problems ❗

Processes


There is no backlog

According to the management workflow we found that there is no scope for future weeks for the development team. Also there is no visible backlog for developers.

Backlog allows team to see the future of the product.

How to fix

Add backlog status to the management board. You can hide it from developers if you wish.

There is no planning meetings

We found that several tasks were estimated by one person, but implemented by other. That’s why sometimes feature’s development time grows so much (60h spent instead of 20h estimation).

How to fix

Once per week/month etc. have a planning session to discuss future workload with the team.

Technical


Incorrect usage of Cubit state

It’s recommended to use different cubit states inherited from the base state.

For example authorisation cubit should have about 4 states: